PgMP Program Management Professional Practice Test | Quiz | #mcq.imBooz

January 9, 2020 by Dr. IM Leave a Comment

Download

1 >>You are the program manager of the JHG Program, and you believe that yourprogram is complete. Stacy Ellison, the program director, refuses to agree thatthe program is closeWhat must be true for the program to be considered completed so that the program director can sign off on the program? Choosethe best answer: ?

  • (A) . All of the program monies must have been spent.
  • (B) All of the program schedule must have been consumed.
  • (C) All of the program component projects must be closed.
  • (D) All of the program risk management activities must be done.

2 >>You have determined that a project in your program must be canceleWhichone of the following is not a valid reason for canceling a project? ?

Download
  • (A) The technology the project will deliver has been surpassed with a newertechnology.
  • (B) The project is not performing well on scope and budget, so the project isterminated.
  • (C) The program has experienced a change to its scope that eliminates theneed for the projects deliverable.
  • (D) The project manager leaves the performing organization.

3 >>When can a project manager release the project resources? Choose the bestanswer: ?

  • (A) When the program manager demands that the project manager do so
  • (B) When the project scope is completed
  • (C) When the project has been officially closed
  • (D) When the project resource is no longer believed to be needed

4 >>You are the program manager for the JHY Program. You are working withseveral different vendors throughout the program, and you need to quicklyreference contract information for one of your vendors. Where can you findthe contract information? ?

  • (A) Centralized procurement
  • (B) Decentralized procurement
  • (C) Contract records management system
  • (D) Contract file

5 >>In order to authorize a project in a program, what document must be created? ?

Download
  • (A) Project scope statement
  • (B) Project preliminary scope statement
  • (C) Project charter
  • (D) Project benefits analysis documentation

6 >>You have chartered a new project in your program. This new project requiresthat you move some of the resources from the HJGY Project to the JHYProject. This allotment of resources from one project to another has causedNancy, the project manager of the HJGY Project, to become frustrated with thechange. All of the following are examples of resources that you, the programmanager, may move from one project to another except for which one? ?

  • (A) People
  • (B) Schedule
  • (C) Monies
  • (D) Equipment

7 >>You are recruiting program team members for your program. Your organizationsrules and policies do not allow you, the program manager, to solicit people fromthe staffing pool directly to join your program team. This is an example of what? ?

  • (A) Human resources best practices
  • (B) Constraint
  • (C) Organizational process assets
  • (D) Staffing pool description

8 >>Virginia needs to speak with Elizabeth regarding a program issue. Elizabeth islocated in another state than Virginias. What document could Virginia use toquickly locate and communicate with Elizabeth? ?

  • (A) Communications matrix
  • (B) Communications management plan
  • (C) Program team directory
  • (D) Program management plan

9 >>You and people from your organization have worked together to createthe program benefits statement. All of the following are not defined in theprogram benefits statement except for which one? ?

  • (A) Program schedule and milestone
  • (B) Program anticipated budget for the initial phase
  • (C) Program business case
  • (D) Organizational benefits of doing the program

10 >>What is the utility function? ?

  • (A) It is a method to quantify the programs risk.
  • (B) It is a stakeholders willingness to pay for the program risk.
  • (C) It is a stakeholders willingness to accept program risks.
  • (D) It is a method to create the risk contingency reserve.

11 >>A portion of your program deals with electrical work. You and your programteam have elected to hire a licensed electrical company to deal with allelectrical work on the program. This is an example of which risk response? ?

  • (A) Mitigation
  • (B) Transference
  • (C) Avoidance
  • (D) Exploit

12 >>All of the following are examples of positive risk responses except for which one? ?

  • (A) Acceptance
  • (B) Exploit
  • (C) Enhance
  • (D) Avoidance

13 >>You are trying to decide if your program should build or buy a piece ofsoftware. You have determined it will cost your program $28,890 to create thesoftware, and itll cost $11,000 to manage the software each month. A vendorhas told you they could create the software for $21,100 and support thesoftware for $9,999 per month. Which is the best decision and why? ?

  • (A) You should buy the software if youre keeping the solution longer than 8months.
  • (B) You should buy the software if youre keeping the solution longer than 18months.
  • (C) You should build the software if youre keeping the solution longer than 8months.
  • (D) You should build the software if youre keeping the solution less than 8months.

14 >>Which contract type is considered the most dangerous for the customer? ?

  • (A) Cost plus incentive fee
  • (B) Cost plus percentage of cost
  • (C) Lump sum
  • (D) Time and materials

15 >>Which contract type is considered the most dangerous for the customer? ?

  • (A) Cost plus incentive fee
  • (B) Cost plus percentage of cost
  • (C) Lump sum
  • (D) Time and materials

16 >>Which contract type is considered the most dangerous for the customer? ?

  • (A) Cost plus incentive fee
  • (B) Cost plus percentage of cost
  • (C) Lump sum
  • (D) Time and materials

17 >>Your organization is participating in a proposal creation for the NHG Corporation. The program is to create a new warehouse for their organization.In this instance your organization is the vendor and the NHG Corporation is the client. What document will you use to determine the expectations of the program you are creating a proposal for? ?

  • (A) Charter
  • (B) Contract
  • (C) Statement of work
  • (D) Preliminary scope statement

18 >>All of the following are examples of constrained optimization except for which one? ?

  • (A) Linear programming
  • (B) Dynamic algorithms
  • (C) Benefit-cost ratios
  • (D) Nonlinear programming

19 >>You are a program manager for your organization. Your program will include seventeen projects over the life of the program. You may create a componentproject at any time in a program except for during what time of the program? ?

  • (A) Initiating
  • (B) Planning
  • (C) Monitoring and controlling
  • (D) Closing

20 >>Which document will serve as an input to the authorize projects process? ?

  • (A) Program charter
  • (B) Project charter
  • (C) Program scope statement
  • (D) Program benefits statement

What is program management professional?

Which is better PMP or PgMP?

Is PMP a prerequisite for PgMP?

How do I get PgMP certified?

Pages: Page 1 Page 2 Page 3 Page 4 Page 5

Filed Under: Competitive Exam Quiz Tagged With: Basic PgMP Program Management Professional objective question, general knowledge quiz, Multiple Choice Questions on PgMP Program Management Professional, pgmp exam questions pdf, pgmp practice exam, PgMP Program Management Professional Practice Test, PgMP Program Management Professional Question answers, PgMP Program Management Professional questions MCQs with answers, PgMP Program Management Professional Quiz, PgMP Program Management Professional quiz game, PgMP Program Management Professional quiz with answers, pgmp question bank, PMI Program Management Professional (PgMP)

Reader Interactions

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Primary Sidebar

Recent Posts

  • Hall Effect, Hall coefficient, Hall potential
  • Ayushman Bharat Yojana Registration, Eligibility, Application form, Check Status
  • Layouts of business letter, types, letter format
  • PMKSNY | PM Kisan Samman Nidhi Yojana | PM Kisan Samman Nidhi gov in | Beneficiary Status
  • 2 मिनट मे पेसा 5 गुना वो भी Binance के Coin से | 5x coin Eearly Binance notification of newly listed
  • 5गुना पेसा पक्का web3.0 Flux coin की पक्की news Top web3.0 coin 100x coin Flux price prediction
  • 2022 मे धूम मचाएंगे Web 3.0 के ये coin | Top Rated web3.0 coin Price Prediction BTT VET Flux LPT
  • 2022 का सबसे अच्छा coin 100 गुना होगा पक्का | Best Coin 100x gems | EGC coin price prediction
  • Top rated web3.0 coin | Flux coin Price prediction | VET coin price prediction 100x coin web3.0 coin
  • WEB3.0 Token BTT coin next 100x gems???? ये जाएगा बहुत ऊपर तक 100रु के 10,000/-

Categories

DMCA.com Protection Status

Footer

Copyright © 2022 · Magazine Pro on Genesis Framework · WordPress · Log in