1 >>What document is created when the program is initiated that defines theprogram benefits? ?
- (A) Benefits mapping plan
- (B) Benefits realization plan
- (C) Program business case
- (D) Program statement of work
2 >>Which program management plan defines the expectations of the programstakeholders? ?
- (A) Program communications management plan
- (B) Stakeholder management plan
- (C) Benefits management plan
- (D) Program management plan
3 >>You are the program manager for the JHN Program. Your program will spanseveral countries, and youll have to adhere to the laws and customs of eachcountry your program will operate within. What entity, in this example, willestablish the rules and procedures your program will follow within yourorganization? ?
- (A) The project management team
- (B) The local government of each country where the program will exist
- (C) The program management team
- (D) The program board
4 >>All of the following are program process groups except for which one? ?
- (A) Program risk management
- (B) Program initiating
- (C) Program closing
- (D) Program monitoring and controlling
5 >>Your boss, Marty, has asked when the planning for your program will end.Whats the correct answer to give Marty? ?
- (A) Planning will end once the program begins executing the program plans.
- (B) Planning will end once the program begins to realize the benefits asplanned for.
- (C) Planning will end once the program moves into the closing process groupactivities.
- (D) Planning never ends.
6 >>What program management plan document helps the program manager andthe program stakeholders visualize the program deliverables? ?
- (A) The program charter
- (B) The program scope
- (C) The program management plan
- (D) The program work breakdown structure
7 >>Your program is moving through rounds of planning. These iterations ofprogram planning are also known by what term? ?
- (A) Demings quality management circle
- (B) Progressive elaboration
- (C) Planning cycles
- (D) Planning refinements
8 >>In which process group does the program management team maintain theprogram schedule? ?
- (A) Planning process group
- (B) Execution process group
- (C) Monitoring and controlling process group
- (D) Closing process group
9 >>There are four reasons a change may be introduced into a program. Whichone of the following is not a legitimate example of why change may occur ina program? ?
- (A) A new vendor is selected for the program
- (B) A value-added change is introduced to the program
- (C) As a response to a program risk
- (D) As a result of an error or program omission
10 >>Every program change must pass through which process to determine theproposed change on the program knowledge areas? ?
- (A) Integrated change control
- (B) Configuration management
- (C) Change control system
- (D) Scope definition planning
11 >>You are the program manager of the JHG Program, and you believe that yourprogram is complete. Stacy Ellison, the program director, refuses to agree thatthe program is closeWhat must be true for the program to be considered completed so that the program director can sign off on the program? Choosethe best answer: ?
- (A) . All of the program monies must have been spent.
- (B) All of the program schedule must have been consumed.
- (C) All of the program component projects must be closed.
- (D) All of the program risk management activities must be done.
12 >>You have determined that a project in your program must be canceleWhichone of the following is not a valid reason for canceling a project? ?
- (A) The technology the project will deliver has been surpassed with a newertechnology.
- (B) The project is not performing well on scope and budget, so the project isterminated.
- (C) The program has experienced a change to its scope that eliminates theneed for the projects deliverable.
- (D) The project manager leaves the performing organization.
13 >>When can a project manager release the project resources? Choose the bestanswer: ?
- (A) When the program manager demands that the project manager do so
- (B) When the project scope is completed
- (C) When the project has been officially closed
- (D) When the project resource is no longer believed to be needed
14 >>You are the program manager for the JHY Program. You are working withseveral different vendors throughout the program, and you need to quicklyreference contract information for one of your vendors. Where can you findthe contract information? ?
- (A) Centralized procurement
- (B) Decentralized procurement
- (C) Contract records management system
- (D) Contract file
15 >>Your boss, Marty, has asked when the planning for your program will end.Whats the correct answer to give Marty? ?
- (A) Planning will end once the program begins executing the program plans.
- (B) Planning will end once the program begins to realize the benefits asplanned for.
- (C) Planning will end once the program moves into the closing process groupactivities.
- (D) Planning never ends.
16 >>What program management plan document helps the program manager andthe program stakeholders visualize the program deliverables? ?
- (A) The program charter
- (B) The program scope
- (C) The program management plan
- (D) The program work breakdown structure
17 >>Your program is moving through rounds of planning. These iterations ofprogram planning are also known by what term? ?
- (A) Demings quality management circle
- (B) Progressive elaboration
- (C) Planning cycles
- (D) Planning refinements
18 >>In which process group does the program management team maintain theprogram schedule? ?
- (A) Planning process group
- (B) Execution process group
- (C) Monitoring and controlling process group
- (D) Closing process group
19 >>There are four reasons a change may be introduced into a program. Whichone of the following is not a legitimate example of why change may occur ina program? ?
- (A) A new vendor is selected for the program
- (B) A value-added change is introduced to the program
- (C) As a response to a program risk
- (D) As a result of an error or program omission
20 >>Every program change must pass through which process to determine theproposed change on the program knowledge areas? ?
- (A) Integrated change control
- (B) Configuration management
- (C) Change control system
- (D) Scope definition planning